Progress of key traffic projects under construction

Progress of key traffic projects under construction Due to continuous rains for several consecutive days in recent days, construction has been unable to proceed, and the progress of the auspicious key projects under construction is now reported as follows:

1. Suxin Expressway Beigou Interconnection Line: At present, in addition to the demolition section of the entire line, subgrade engineering and bridge and culvert engineering are under construction, and subgrade engineering is completed by 30%.

2. X308 Lake West Dettige: Cement concrete pavement construction is currently underway, and the single-spot construction is approximately 14 kilometers.

3. Outer ring northwest of the city: At present, the roadbed construction on both sides is being widened, and the subgrade project has been completed 80%.

4. Tanggang Road Extension and Widening Reconstruction Project: At present, the subgrade project has been completed and 12% limestone basement construction is underway. The construction is completed by about 6km.

5. The reconstruction project of X210 Hefei line: At present, the subgrade project has been completed and 12% of the limestone basement is under construction. About 70% of the construction is completed.

6. Danger bridges on rural roads and rural roads: All construction bids have been completed.

Spray equipment is used to fall dust in the air.Open Spaces: such as coal fields, mines, cement plants, garbage dumps, construction sites;Industry: such as steel industry, chemical industry, cement plant, thermal power plant;
City construction:city greening, city cleaning, community purification,and so on.
0100

Spray Cannon

Spray Cannon,Spray Confetti Cannon,Spray Machine,Spray Streamer Cannon

SHANDONG HUALI ELECTROMECHANICAL CO.,LTD , http://www.shanhuachina.cn

This entry was posted in on